Project Overview
Project updates and information for the phase 1 project area: Valley Drive/Evergreen Subdivision

Virtual Information Meeting, Nov. 30, 2022
- Meeting Video (YouTube) *Due to a recording issue, presentation slides aren't visible in the video.
- Meeting Presentation Slides (PDF)
Valley Drive/Evergreen Subdivision Open House, Oct. 16, 2024
Public Engagement Summary
Updates
July 2025
February 2026
Capital Improvements - In Progress
- Staff are working on property and easements acquisitions
- Staff are evaluating the feasibility of the installation of a storm sewer on Dexter – submitting to MDOT for approval or denial
- Staff are working on preliminary designs for the regional stormwater storage ponds
June 2026
Capital Improvements - In Progress
Staff continue to work towards implementation of proposed recommendations from Phase I. One of these recommendations included installing a larger, enclosed stormwater pipe to convey more water westward along Dexter Road and away from private properties while working on the Dexter Road Sidewalk Project; please visit the project webpage to see the design plan for that project.
Due to a recent and unforeseen permit denial by another agency, this recommendation can no longer occur. City staff are working with engineering consultants to design alternatives to manage stormwater coming from north of Dexter. As the city moves forward with its Capital Improvement Plan, staff will ensure the new sidewalk is coordinated with any revised strategies for stormwater management.