Overview

Utility upgrades, road resurfacing, and an updated streetscape to be constructed on Ann Street from First to Fifth. Construction is planned to be completed in Fall 2026. The project will be done in phases:

Schedule:

Phase 1 – Complete

Phase 2 – Closure of North Main Street and Ann Street Intersection: July 29-Sept. 17, 2026

Phase 3 – Main Street to Fifth Avenue: September – November, 2026

The schedule is subject to change.

For information on road closures associated with this and other projects, please visit the city's road and lane closures page.

Why is this project being done?

The existing water main along Ann Street is over 100-years old and is undersized. The roadway is also in bad condition and needs to be replaced. This project will replace aging infrastructure, fix the road surface, improve stormwater drainage, and update the streetscape. In 2025, residents and business owners in the area were engaged to solicit their ideas and concerns, and to share the design concept.

Work to be done:

  • Replace the old water main with a larger pipe between N. First Street and N. Fifth Avenue.
  • Add new stormwater drainage between to reduce the risk of flooding
  • Resurface the roadway
  • Build permanent curb extensions at intersections
  • Update the streetscape and replace unhealthy trees

Funding sources:

  • Water main work will be paid for by the Water Supply System Fund.
  • Stormwater system improvement will be paid for by the Stormwater Fund.
  • Repaving will be funded by the Road, Bridge, and Sidewalk Millage Fund.
  • Streetscape upgrades will be funded by the Ann Arbor DDA.

August 7, 2026

  • Phase 2 of the project began Wednesday July 29.
  • The intersection at Ann Steet and North Main Street is closed for the month of August.
  • Detour signs are posted, please continue following the posted vehicle and truck detours
  • Pedestrian traffic will be maintained through the intersection during construction
  • There will be changes to pedestrian traffic detours as needed to complete the work, please watch for changes to pedestrian detours.
  • Work details:
    • Past: The watermain is installed in the intersection
    • Present: Crews have moved to installing stormwater infrastructure and testing and disinfecting the water main
    • Future: Storm installation will continue. Water main tie-in is currently scheduled for the week of August 17.
    • Impacts: Some water services near the intersection will be temporarily interrupted so the existing water main can be shut down, and the new water main can be connected. Affected businesses and residents will be notified prior to planned shutdowns.

July 22, 2026:

  • The Ann Street and North Main Street intersection will be closed beginning Wednesday, July 29, as Phase 2 work gets underway.
  • The intersection is expected to reopen in September, weather permitting.
  • Business access will be maintained.
  • Customers, deliveries and other local traffic will continue to have access to businesses on Ann Street and North Main Street.
  • The alley off Ann Street will be accessible from Ashley Street to Ann Street.
  • Clearly marked detours will direct drivers around the work zone.
  • Business Access
    • Most on-Street parking on Main Street will remain available; the southern three spaces on both sides will be blocked off for a safe turnaround.
    • Local access on Ann will be maintained.
    • Sidewalk access will remain open (sidewalk ramps at Ann and Main will be closed and detoured temporarily when needed.)
    • Delivery access will continue. Large delivery vehicles will be detoured from M-14 to Maple to Jackson/Huron.
    • The Ann Ashley Parking Structure will remain open and can be accessed from Ann Street west of North Main Street or from North Ashley St.
  • For detour information for this closure, as well as any others within the city, please visit a2gov.org/roads.

Rendering of Ann Street and North Main Street intersection improvements:


May 26, 2026:

  • Phase 1 will be paved Wednesday, May 27 and Thursday, May 28.
  • The road will be fully opened to traffic by June 5, after pavement markings and structure adjustments are complete.
  • The parking structure will be reopened by June 5 to full capacity for the rest of the project.
  • Phase 2 is scheduled to begin in late July. This is to ensure that N Main Street is fully opened to traffic for the Ann Arbor Art Fair.

May 14, 2026:

  • Underground utility installation between First and Main is complete and concrete work is underway, followed by grading and paving of the roadway.
  • This work is expected to be completed in early June, rather than the originally targeted mid-May timeframe. This schedule change is due to weather, conditions in the field, and to ensure quality of work.
  • Upon completion of Phase 1, the roadway and parking structure will be reopened.
  • Phase 2 is scheduled to begin in late July. This is to ensure that N Main Street is fully opened to traffic for the Ann Arbor Art Fair.

April 21, 2026:

  • Water main has been installed from First to Main and is being disinfected and tested.
  • Once testing is complete, temporary water service interruptions will be required. Impacted properties will receive an orange door hanger prior to the shutdown with additional details.
  • Installation of other underground utilities will continue throughout the week.
  • Crosswalks are open at all intersections. Please follow the pedestrian detours and do not go around barricades. This is for your safety and the safety of others.

Photo showing construction on Ann Street


March 26, 2026:

Detour signage has been installed, and a marked route is in place. Navigation platforms, including Google Maps, Apple Maps, and Waze, have been updated to reflect current closures and detours.

Access to the Ann Ashley parking structure must be made from Miller Avenue to North Ashley Street. Due to the closure of the Ann Street exit, the parking structure capacity will be limited through Mid-May. Parking Permit holders are always guaranteed a spot, even if the sign says full. Please see the 'Traffic, Parking & Access Impacts' tab for more details.

The city is working closely with the Downtown Development Authority (DDA) and the parking structure operators to alleviate congestion and confusion. We will monitor usage and will adjust available spaces to allow as much hourly parking as possible. We are working to balance parking needs with logistical considerations and will continue to fine tune operations as the first phase of the Ann Street project progresses.

The 16 trees on Ann Street between the parking structure and Fourth Avenue will be removed Saturday, April 4. On-street parking on Ann Street will be prohibited from Main Street to Fourth Avenue on April 4 for the work to be done. The work will last one day. New trees will be planted in new tree grates as part of the DDA’s streetscape portion of the project.


March 20, 2026 Update:

Construction of Phase 1 will begin, as planned, on Monday, March 23. Ann Street will be closed from First Street to Main Street; driveways on Ann Street will still be accessible. Ashley Street will be closed at Ann Street and First Street while Main Street will remain open. The Ann/Ashley parking structure will be accessible off Ashley Street. A detour will be posted on Monday, March 23.

Water main will be installed first. It will be installed along the south curbline from West to East.

The 16 trees on Ann Street between the parking structure and Fourth Avenue will be removed before April 15, per federal guidelines. If you have any lights in these trees, please remove them before April 1.


March 6, 2026 Update:

We are pleased to share that Bailey Excavating, Inc. has been awarded the construction contract for the Ann Street Improvements Project. Construction is scheduled to begin March 23, 2026. Construction will be completed in three (3) phases from west to east. A map of the phases is provided below.

As work gets underway, we encourage everyone within the project area to stay informed by joining the project mailing list. To receive timely updates, please click the “+Follow” button at the top of this page to be added to the mailing list for construction updates.

We appreciate your continued patience and support as we move into the construction phase and look forward to delivering these important improvements to the Ann Street corridor.


January 26, 2026 Update:

A rendering of the final design for Ann Street has been posted.

Please visit the website to view how the road is going to look when the project is complete. The on-street parking spaces are identified on the plan.

Some notable changes from the preliminary rendering are:

  • Bump outs at the intersections were extended to prevent parked cars from being too close to intersections.
  • A fully accessible on-street ADA parking space was added near Main St. The design will be the same as the newly installed ADA space on Fourth Ave north of Huron St.
  • Two more disabled on-street parking spaces were also added to the corridor. These are standard parking dimensions, but a person must have a disabled placard to park there.
  • The Sharrow bike symbols were removed.

The major changes from the current layout include:

  • The bike lane was removed. There was no room for a two-way bike lane and there is a high-comfort, two-way bike lane one block north on Miller/Catherine.
  • A mid-block crosswalk will be added by the Ann-Ashely parking structure.
  • The long curb cut in the northwest quadrant of Ann St. and Main St. will be closed and on-street parking will be added on both sides of the road.
  • A unified street design, including garden beds, streetlights, benches, and bike hoops, will be installed from Ashley St. to Fifth Ave.
  • Most of the on-street parking and loading zones will stay the same.

The project is out to bid right now, and the City will open proposals next week. Construction is expected to start in April and be completed in three phases. The road will be completed by November of 2026. An informational video will be posted to the website in February to explain the phases and impacts of construction.

  • Streets will be closed to thru traffic. Access to homes and businesses will be maintained but may include delays during working hours. Deliveries to businesses will be coordination directly with the business owner.
  • On-street parking may be temporarily unavailable within the project area.
  • Temporary water shutoffs are required and will be communicated in advance.
  • Construction will cause noise, dust, and temporary parking changes.
  • Mail, deliveries, garbage, compost and recycling will be accommodated.
  • Work will take place within the City Right-of-Way, including storing materials required for the project. Any disturbed area will be restored after the project is completed.
  • Construction notices will be delivered prior to construction.

Traffic, Parking, and Access

Vehicles: Estimated road closure dates:

  • July 27 - Early September: Full closure of Main and Ann intersection
  • September 8 - Mid-November: Full closure of Ann from North Main to Fifth Avenue
  • Partial Closure of Fifth Avenue from Catherine to Ann; west lane and bike lane closed for temporary bus loading zone

Parking:

  • The Ann Ashley Parking Structure will remain open and can be accessed from Ann Street west of North Main Street or from North Ashley Street.
  • Other parking options:
    • Library Lane structure (319 S. Fifth)
    • Fourth & Washington structure (123 E. Washington)
    • Fourth & William structure (115 E. William)

Pedestrians:

  • Sidewalk access will remain open. Please follow the pedestrian detours and do not go around barricades. This is for your safety and the safety of others.


Project Design

From April 11 to May 30, 2025, the Ann Street Corridor Experience form was available for business owners and residents to share their experiences as well as concerns when traveling the Ann Street Corridor.

August 13, 2025: An in-person public meeting was held to share the design concept.

January 14, 2026: The design concept was finalized

Final project design

Click the image to expand image