Project Overview
The Worden Avenue petition has been completed. Construction is anticipated May 2025.
Why is this project being done?
This project is being completed to address speeding concerns and cut-through traffic on Worden Avenue.
Work to be done
Two speed bumps and one curb extension will be installed on Worden Avenue between Jackson Avenue and Dexter Avenue.
Funding Source
Washtenaw County's Public Safety and Mental Health Preservation Millage
- Qualification Criteria Matrix (PDF) - Jan 2024
- Initial Questionnaire Summary (PDF) - Feb 2024
- Final Poll Letter & Results (PDF) - Aug 2024
- Save-the-Date Postcard (PDF) - Feb 2024
- Meeting 1 Presentation (PDF) - Apr 2024
- Meeting 1 Recording - Apr 2024
- Meeting 1 Discussion Summary (PDF) - Apr 2024
- Device Images & Descriptions (PDF) - May 2024
- Meeting 2 Presentation (PDF) - Jun 2024
- Meeting 2 Recording - Jun 2024
- Meeting 2 Discussion Summary (PDF) - Jun 2024
- Final Plan (PDF) - Jul 2024
Installation of calming devices is anticipated to begin May 2025 and last approximately 4-6 weeks weather dependent. Installation will occur in phases to minimize impact to residents.
Temporary impacts include:
- Temporary restricted on-street parking
- Closures to one lane
- Intersections may be closed for limited time to allow for installation and curing of devices
Please adhere to all detour and parking restriction signs during construction to ensure a safe and quick project completion.
Project Boundaries

Worden Avenue Traffic Calming Project extent