Project Overview
The Manchester Road public engagement process has concluded. This project was approved by City Council in September 2023; construction is scheduled to start Spring 2024.
UPDATE: Due to a conflicting project in the area. Construction has been moved to late fall 2024.
Why is this project being done?
This project was completed to address speeding concerns and cut-through traffic on Manchester Road.
Work to be done
Two speed humps were installed on Manchester Road between Needham Road and Buckingham Road.
Funding Source
Washtenaw County's Public Safety and Mental Health Preservation Millage
- N/A
- Qualification Criteria Matrix (PDF) - Jan 2023
- Initial Questionnaire Summary (PDF) - Feb 2023
- Final Poll Letter and Results (PDF) - Aug 2023
- Save-the-Date Postcard (PDF) - Apr 2023
- Meeting 1 Presentation (PDF) - Apr 2023
- Meeting 1 Recording - Apr 2023
- Meeting 1 Discussion Summary (PDF) - Apr 2023
- Device Images and Descriptions (PDF) - May 2023
- Preliminary Plan (PDF) - May 2023
- Meeting 2 Presentation (PDF) - Jun 2023
- Meeting 2 Recording - Jun 2023
- Meeting 2 Discussion Summary (PDF) - Jun 2023
- Final Plan (PDF) - Jul 2023
- REVISED Final Plan (PDF) - March 2024
- Final Plan Revision Letter (PDF) - March 2024
Project Boundaries
Manchester Rd Traffic Calming project extent