Project Overview
The Henry Street Traffic Calming Project was approved by Council at the June 3, 2024 meeting; construction is completed.
Why is this project being done?
This project was completed to address speeding concerns and cut-through traffic on Henry Street.
Work to be done
Four speed humps were installed on Henry Street between Golden Avenue and Packard Street.
Funding Source
Washtenaw County's Public Safety and Mental Health Preservation Millage
- Save-the-Date Postcard (PDF) - Sep 2023
- Meeting 1 Presentation (PDF) - Oct 2023
- Meeting 1 Recording - Oct 2023
- Meeting 1 Discussion Summary (PDF) - Oct 2023
- Device Images & Descriptions PDF) - Nov 2023
- Meeting 2 Presentation (PDF) - Nov 2023
- Meeting 2 Recording - Nov 2023
- Meeting 2 Discussion Summary (PDF) - Dec 2023
- Final Plan (PDF) - Dec 2023
Project Boundaries

Henry Street Traffic Calming Project extent